waste QLD STATE Cross River Rail Delivery Authority / Department of Transport and Main Roads
$13.6B

Cross River Rail: $13.6 Billion Blowout — 253% Over Budget

Cross River Rail was budgeted at $5.4 billion and is now costing $19.04 billion — a $13.6 billion overrun, 253% over budget. Completion pushed from 2024 to 2029+. Workforce shortages, 148 days of industrial strikes in 2024, and supply chain failures drove the blowout. The largest single infrastructure failure in Queensland history.

✉ Take action
Email your federal MP

Enter your postcode. We'll find your MP and pre-draft a letter about Cross River Rail Delivery Authority / Department of Transport and Main Roads's $13.6B in waste — ready to send from your email.

Your name (optional):

Opens your email app with a pre-filled message. You send it — we don't collect your name or email.

What This Means

$13.6B of Australian taxpayer money was wasted at Cross River Rail Delivery Authority / Department of Transport and Main Roads. Cross River Rail was budgeted at $5.4 billion and is now costing $19.04 billion — a $13.6 billion overrun, 253% over budget. Completion pushed from 2024 to 2029+. Workforce shortages, 148 days of industrial strikes in 2024, and supply chain failures drove the blowout. The largest single infrastructure failure in Queensland history.

Spread across Australia's 10.8 million households, that's roughly $1,263 per family — enough in total for funding roughly 114 public hospitals for a full year.

  • Cross River Rail was budgeted at $5.4 billion and is now costing $19.04 billion — a $13.6 billion overrun, 253% over budget.
  • Workforce shortages, 148 days of industrial strikes in 2024, and supply chain failures drove the blowout.
  • The largest single infrastructure failure in Queensland history.
Amount Spent
$19,040,000,000
Original Estimate
$5,400,000,000
Waste / Overrun
$13,640,000,000
Cost Overrun
253%

Analysis

Category: waste
Severity: critical
Agency: Cross River Rail Delivery Authority / Department of Transport and Main Roads
Fund This Investigation
Fund the Investigation
Your donation funds more investigations. 100% goes directly to accountability work.
Choose an amount
$
Secure payment via Stripe. 100% funds accountability work.
Share this finding

Every share puts pressure on the people responsible. Make it impossible to ignore.

The Daily Reckoning
Get every new finding in your inbox.

I send every new finding. Daily. No fluff.

Related Findings
Major Transport Infrastructure
$125.0B

Suburban Rail Loop: $34.5B to $216B — The Costliest Infrastructure Promise in Australian History

Department of Veterans' Affair
$59.7B

DVA military compensation liability surged $59.7B in a single year — up 65%

NBN Co
$27.5B

NBN Co $27.5B cost blowout — 93% over original $29.5B estimate

Department of Home Affairs
$23.8B

11 of 14 Home Affairs SES officers skipped conflict of interest declarations on $23.8B contract portfolio

Major Transport Infrastructure
$19.0B

Victorian Big Build: West Gate Tunnel + Metro Tunnel + North East Link — $19B in Combined Overruns